Production Targets Definition | Production Target Formula | Examples of Production Targets | Industrial Engineering Formula | IE Formula for Garments
Daily Production Target in Garment Industry:
Production quantity produced by a qualified worker in a day at standard performance is known as daily production target.
Daily production target can be calculated by using the below formula in apparel industry:
Daily production target,
= (Daily clock minute/ Standard time) × Efficiency
= [{(No. of operator × working hours × 60) / Standard time} × Efficiency]
The above formula will be very easy to understand if you follow the below examples.
Fig: Readymade garment floor |
Example-01:
In a production line of Rahela Apparel Limited have 40 operators, where working hours is 10, standard time 90 minutes and 80% expected efficiency. Find out the expected production target per day in that factory.
Solution:
Here,
Number of operators= 40,
Number of working hours= 10,
Standard time= 90 minutes,
Expected efficiency= 80%,
Production target per day=?
Daily production target = (Daily clock minute/ Standard time) × Efficiency
= [{(No. of operator × working hours × 60) / Standard time} × Efficiency]
= [{(40 × 10 × 60)/ 90} × 80%]
= 213 pcs.
So, daily production target in Rahela Apparel Limited is 213pcs.
Example-02:
Number of working hours= 08,
Number of operators= 50,
Expected efficiency= 85%,
Standard time= 80minutes
By following the above points of Tawhida Apparel Limited, find out the daily production target in that factory.
Solution:
Here,
No. of working time= 8hours,
Total no. of operator= 50,
Standard time= 80min,
Efficiency= 85%,
Per day production target=?
Daily production target,
= (Daily clock minute/ Standard time) × Efficiency
= [{(No. of operator × working hours × 60) / Standard time} × Efficiency]
= [{(50 × 8 × 60)/ 80} × 85%]
= 255pcs.
So, daily apparel production target in Tawhida Apparel Limited is 255pcs.